Project Name Cost Estimates
Alpharetta (Kimball Bridge Rd) Water Transmission Main $9,200,000
Gap II (Buice Rd & Kimball Bridge Rd) 54" $12,000,000
Providence Water Main $5,970,000
Hwy 141 Water Main Addition $2,340,000
North Coleman (Shallowford Road) $2,635,000
Birmingham Water Main Loop
Water Security $500,000
Water Tank Painting $1,450,000
Other $7,695,000
Total Water System Capital Improvement Projects: $41,790,000
Little River WRF Expansion Design $1,110,000
Little River WRF Expansion $30,000,000
Chattahoochee III Pump Station $2,000,000
Willeo Creek Pump Station $520,000
Hopewell Road Pump Station $1,000,000
Crooked Creek Pump Station $1,000,000
Riverchase Pump Station $330,000
River Bluff Pump Station $150,000
Little Riverside Pump Station $150,000
Windward Villiage Pump Station $100,000
Blessed Trinity Pump Station $3,000,000
Pine Bloom Pump Station $100,000
Cameron Glen Pump Station elimination $1,000,000
Cobb Willeo Pump Station $1,500,000
Ball Mill Pump Station $1,500,000
Camp Creek Pump Station $2,500,000
Graham Drive Pump Station $1,800,000
Morning Creek Pump Station $1,600,000
Cochran Road Pump Station
Great Southwest Pump Station $700,000
Deep Creek Pump Station
Stone Wall Pump Station
White Water Pump Station $2,500,000
Big Creek WWTP $225,000,000
City of Atl Plant Improvements (IGA Cost Share) $3,000,000
Big Creek to Cobb Diversion $23,000,000
Johns Creek Environmental Campus Reuse Main $10,000,000
Camp Creek WRF Improvements $10,000,000
Big Creek WRF Immediate Needs $66,000
Big Creek WRF Immediate Needs Construction $9,000,000
Other $3,400,000
Total Wastewater System Capital Improvement Projects: $336,026,000
Standby Engineering $15,000,000
Standby Misc. Construction - Emergency Water System $30,000,000
Standby Misc. Construction - Wastewater System $45,000,000
Standby Misc. Pipe Lining and Pipe Bursting $9,000,000
Standby Water Meter Replacement $10,700,000
Water and Sewer Relocation Due to Road Widening $16,000,000
Water and Sewer Relocation Due to Road Widening $20,000,000
Total Standby Capital Improvement Projects: $145,700,000










 
 